Latest news



March 21st 2025
Plots 2 & 3 progressing well. The Brickwork is almost complete. The Roof Trusses are being installed and the Case Manager, OT and Solicitor acting as Guardian for the buyer are on site inspecting the work and finalising the internal layout changes we have been discussing over the past three months.


Latest news
December 23rd 2024
Plots 2 & 3 concrete foundation slab has now been laid and facing brickwork delivered ready for the shell to commence building. The 150mm thick Insulation and 60mm screed floor will be laid after the shell and roof have been completed.

Latest news
December 23rd 2024
Plot 1 ready for a sand blinding and then pouring the concrete foundation slab on 6th January 2025.


Latest news
November 15th 2024
At last! The piles have been capped with the Ringbeam re-enforced mesh and now being concreted. Work on the brickwork sub structure for the slab can commence next week.

Latest news
October 1st 2024
AND WE'RE OFF!! Work started today on the foundations for the bungalows.
Hopefully, the weather will be good the next couple of days to make good progress (or complete) the foundations for plots 2 &3.

Latest news
September 18th 2024
The site has been cleared and ready for the groundwork to commence on the foundations.